The Financial settlement of the “Renovation and safety works in the Orangery building” task with the General Contractor is in progress

Oranżeria, fot. W. Holnicki; C109220.jpg

On 28 December 2018, all the planned construction works on the Orangery building, related to the implementation of the “Renovation and safety works in the Orangery building” task were completed. In December, there was also a formal settlement of works with the second Contractor on the task.

However, to date, the settlement procedure with the General Contractor of the renovation and safety works in the Orangery building – Renova Sp. z o.o., with which on 31 July 2018 the Museum of King Jan III’s Palace in Wilanów withdrew from the concluded Contract, has not been completed.

In the course of activities aimed at the legal and formal termination of cooperation with Renova Sp. z o.o., on 11 November 2018, the Museum of King Jan III’s Palace in Wilanów received a notice of bankruptcy of the above mentioned company with a summons to file a claim from the bankruptcy estate receiver assigned by the court, and in the following days, the Museum contacted the attorney of the receiver.

Based on the notification, on 13 December 2018, the Museum of King Jan III’s Palace in Wilanów filed a declaration of its claims with the 10th Commercial Department of the District Court for the Capital City of Warsaw.  

At the same time, in correspondence with the receiver, the Museum of King Jan III’s Palace in Wilanów supported the declaration of cooperation on the final settlement with the Bankrupt – General Contractor.

However, detailed arrangements are being made to this day with the receiver in this matter.

logotypy POIiŚ3

2019-04-24
Rabata przed Oranżerią, fot. Ł. Przybylak

Problems with carrying out the “Renovation and safety works in the Orangery building” task

“Something is rotten in the state of Denmark” – this quotation from William Shakespeare’s Hamlet perfectly reflects the current state …

prace-w-oranzerii-koniec-fot-k-kusmierska.jpg

Completion of ‘Repair and preventive works in the Orangery building’

Stormwater sewer and lift station at the Orangery building are ready. Construction works were completed on 28 December 2018. The …

Biuletyn Informacji Publicznej Biuletyn Informacji Publicznej

Museum in Internet

Organizer

Partners

Sponsors

Idea & Design
Copyright © Muzeum Pałacu Króla Jana III w Wilanowie

We would like to inform that for the purpose of optimisation of content available on our website and its customisation according to your needs, we use information stored by means of cookies on the Users' end devices. You can control cookies by means of your Internet browser settings. Further use of our website without change of the browser settings means that you accept the use of cookies. For more information on cookies used by us and to feel comfortable about this subject, please familiarise yourselves with our Privacy Policy.

✓ I understand